Case Study: Infrastructure Grading (JVC)

Road Sub-Base Grading & Compaction Ahead of Asphalt

The Challenge

An infrastructure contractor working on internal roads in Jumeirah Village Circle needed sub-base grading and compaction finished ahead of an asphalt crew already booked for the following week — leaving no room for rework.

Our Approach

Phase 1: Cut & Fill to Design Levels

Our CAT 18 grader cut and filled the road corridor to the design cross-section, checked continuously against the civil drawings.

Phase 2: Sub-Base Compaction

Bomag single-drum rollers compacted the sub-base in layers to the specified Proctor density, with density checks between passes to catch any soft spots before they became a problem under asphalt.

Phase 3: Final Grade Check & Handover

A final grader pass and level survey confirmed the road bed was within tolerance for the asphalt team, and we handed over documentation covering every compaction test.

The Result

The sub-base was signed off and handed to the asphalt contractor two days early, with compaction records that satisfied both the client and Dubai Municipality inspection.

Infrastructure Grading (JVC)Infrastructure Grading (JVC)

Equipment Used On This Job

Grader CAT 18SALE

Grader CAT 18

Operating weight: ~37,000 kg (37 t)
Heavy (20t+)Wheeled
Drum Roller Bomag BW 211

Drum Roller Bomag BW 211

Operating weight: ~13,000 kg (13 Ton)
Medium (5-20t)
Motor Grader CAT 120M

Motor Grader CAT 120M

Operating weight: ~18,460 kg (18.4 t)
Medium (5-20t)Wheeled